Your Power Bills Are Paying for Power Plants That Sit Idle, Here's Why
News

Your Power Bills Are Paying for Power Plants That Sit Idle, Here’s Why

Pakistan should check its electricity needs before it approves new power plants, says the Independent System and Market Operator (ISMO). Rooftop solar and uncertain demand could leave plants idle. Consumers would still pay their fixed costs through electricity bills.

ISMO shared the warning in its Integrated System Plan for 2026 to 2036, which it wrote with the National Grid Company of Pakistan. The plan says the country may not need more plants. It needs a smarter system that manages power from different sources, stores extra solar energy and delivers electricity when people need it.

The plan expects overall electricity demand to grow by 3 percent a year until 2036. Power from the national grid will grow by only 1.75 percent a year, though. More homes and businesses now make their own electricity with solar panels. Peak demand will rise from 26,768 megawatts in FY2025 to 35,127 megawatts by FY2036.

This creates a problem for the grid. During the day, solar panels cut the electricity people buy from power companies. After sunset, consumers rely on the grid again. The country must keep enough plants ready for evening demand, even if they sit idle during the day.

Idle capacity makes electricity costlier. Power plants have fixed costs whether they produce electricity or not. When the grid sells fewer units, those costs spread over less power. This raises the capacity charges that consumers pay per unit.

ISMO says the government should try other steps first. These include better electricity management, time-based tariffs and energy-saving measures.

Under the main forecast, installed capacity will rise from about 39,141 megawatts in FY2026 to 52,527 megawatts by FY2036. The plan includes 8,664 megawatts of committed projects and 7,942 megawatts that ISMO picked through its planning process. About 3,219 megawatts of old capacity will retire.

ISMO did not pick any new fossil-fuel or imported-fuel plants in any of its three demand scenarios. It prefers hydropower, nuclear, solar and wind, with battery storage to support them.

Under the main scenario, the expansion would cost $44.2 billion in present value. This is a planning estimate, not a bill due now. The plan also does not force the government to buy power from every project on the list.

ISMO proposes adding 1,740 megawatts of battery storage by FY2036. This includes 1,000 megawatts for the national grid, which the plan says should come in two phases by March 2029. Batteries store solar power during the day. They release it in the evening, when demand stays high but solar output drops.

The report also calls for other upgrades:

  • Better transmission lines to move power where people need it
  • Stronger links between the national grid and K-Electric
  • Better power supply in areas such as Gwadar and Makran
  • Programs that encourage people to use electricity outside peak hours
  • Better energy efficiency in buildings, especially to cut summer cooling demand

ISMO studied three demand scenarios. Under low demand, peak demand could reach 32,965 megawatts by FY2036. Under high demand, it could reach 43,765 megawatts.

This gap shows why long-term projects need careful planning. If demand grows slower than expected, new plants could sit underused. That would push up electricity costs for consumers.

The plan says transmission projects, both ongoing and planned, will need about $9.176 billion. ISMO also warns that delays in big hydropower and transmission projects could raise costs and disrupt supply, even if the country has enough generation capacity. It advises the government to check project costs, track actual demand and avoid unnecessary commitments.

The plan’s main message is clear. Pakistan should rethink how it manages electricity instead of simply adding more plants. As more consumers make their own solar power, the country needs better storage, stronger transmission and smarter demand management. This will keep power available when people need it without adding extra costs to their bills.